Update: Curb Repairs

March 22, 2017

March 22, 2017

On Monday, March 27th, saw cutting and removal and replacement of the curbs on Main Street will begin.

 

January 26, 2017

Avilla has awarded a contract to Pulver Asphalt Paving to remove and replace the curbs on both sides of Main Street from 4th Street. to Fischer Street.

All driveway on approaches on Main Street will be replaced with new concrete.   The street will then be milled and resurfaced.

The project will begin no later than March 13th and will be finished by June 30th.

Access to driveways will be limited while they are working in the area.

 